Commissioning
The plant has now been installed. Connections of electricity and water are ready and compression tests can be made. Final tests are made before the commissioning, including:
-
Cold testing.
-
Drying out the lining in combustion chamber.
-
Check of performance fuel.
-
Commissioning for commercial heat utilization.
-
Hand-over instruction and maintenance manuals to the customer.
-
Plant is checked by the authorities.
-
Trial runs.
-
Training of the operating personnel.
This stage is concluded when the plant is operating and handed over to the customer. The plant is covered by the warranty described in the contract and our service department is ready to assist the customer in case of problems.
Proceed to stage 8 of the stage-gate process, warranty. |